California bullet train takes major step towards completion

California bullet train takes major step towards completion

The California High-Speed Rail Authority (CHSRA) approved some $1.6 billion worth of track and systems work for a piece of the $20 billion Bakersfield-to-Merced bullet train

The Authority said the procurement schedule should allow it to meet its Dec. 31, 2022, Federal Railroad Administration deadline for completion. This is a critical goal if the authority wants to hold onto a $928.6 million Federal Railroad Administration (FRA) grant for the project.

In May, the FRA notified the CHSRA that it had terminated the grant because the authority had not made sufficient progress on the bullet train and would likely not meet the deadlines outlined in the grant agreement. The FRA also accused the authority of failing to make “reasonable progress” on the project and mismanaging its administrative duties. In addition, it said it might try to claw back $2.5 billion of American Recovery and Reinvestment Act funds as well.

A few days after receiving the federal government’s grant cancellation notice, the state of California and the CHSRA sued the USDOT and the FRA in an attempt to stop them from terminating the financing agreement. In the lawsuit, the state claims that it has met its obligations under the grant agreement and that, in fact, the federal government had not kept up with its responsibilities to the project.

The FRA said one of the other factors it considered when making its decision to rescind the grant was California Gov. Gavin Newsom’s order that the $79 billion Northern California-to-Southern California bullet train route be scaled down to just the Bakersfield-to-Merced route. This changed the nature of the project, according to the FRA. ​